Zandam Cheese & Piggery – Durbanville

Logo ibert

ibertZandam (Pty)Ltd.

Construction Year: January 2016 – August 2016
Commissioning: September 2016

Feedstock:

Pig manure 5 – 7,5 % DM
daily feeding: 45 to

Installation:

Pre pit for feedstock, Mixer and Screen Press for solid content upgrading from ~5% to 10% DM, Chopper Pump with cutting blades.
500 cbm Double Chamber Digester ibert Digester system, in – and outlet pipes.
Storage Tank ibert DIY-Digester system 200 cbm, gas line connected with underground gas cooling.
Technic Container with hot water manifold, CHP and electrical room

Energy:

CHP MAN 75 kW el. and 105 kW them.

Pre heating hot water system with 300l and 500l double coil water tanks.